SMA WB 3600TL User Manual

Page 51

background image

SMA Solar Technology AG

Initial start-up

Installation Guide

WB36TL_50TL-IEN102011

51

3. Switch on the line circuit breaker.
4. Commission the small wind turbine system in accordance with the instructions of the

manufacturer.

5. If available, connect the supply voltage of the multi-function relay.
6. Check whether the display and LEDs are indicating a normal operating state.

☑ Successful commissioning is indicated by a glowing or blinking green LED.

The meaning of the illuminated red LED and the meaning of the event numbers on the display
are described in section 11.2 ”Error Messages” (page 71).

CAUTION!
The Electronic Solar Switch can be damaged if it is inserted incorrectly.

• Firmly connect the Electronic Solar

Switch.

• Check firm position of the Electronic

Solar Switch.
The handle of the
Electronic Solar Switch must be flush
with the housing.

LED

Color

Description

A

Green

Glowing: operation
Flashing: network
connection conditions not
yet reached. The inverter
only switches to network if
the conditions are met.

B

Red

Disturbance

C

Blue

Bluetooth communication is
active