beautypg.com

2 all installations (except massachusetts), 9 ac electrical power wiring – AERCO BMK 6000 Dual Fuel User Manual

Page 25

background image

Benchmark 6000 DF Installation, Operation & Maintenance Manual

CHAPTER 2 – INSTALLATION

OMM-0096_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 25 of 219

GF-141

Ph.: 800-526-0288

03/21/2014

2.8.3.2

All Installations (Except Massachusetts)

For all installations (other than Massachusetts) that EXCEED 1 PSI gas pressure, a mandatory
external gas supply regulator must be positioned as shown in Figure 2-8. No regulator is required
for gas pressures below 1 PSI of pressure. Consult the local gas utility for detailed requirements
concerning venting of the supply gas regulator.

Figure 2-8. Manual Gas Shut-Off Valve Location

2.9 AC ELECTRICAL POWER WIRING

The AERCO Benchmark Electrical Power Wiring Guide, GF-2060, must be consulted prior to
connecting any AC power wiring to the unit. External AC power connections are made to the unit
inside the Power Box on the front of the unit. Remove the unit’s front panel to access the Power
Box, which is mounted in the upper right corner of the unit as shown in Figure 2-9. Loosen the
four Power Box cover screws and remove the cover to access the AC terminal block
connections, and other internal components shown in Figure 2-10.

NATURAL

GAS

SUPPLY

PROPANE

GAS

SUPPLY

MANUAL

SHUT-OFF

VALVES

GAS PRESSURE REGULATORS