beautypg.com

5 i/o signal timings – IAI America PCON-CFA User Manual

Page 248

background image

5. Flow and Commands of Basic MECHA

TROLINK Communication


242


5.5 I/O

Signal

Timings


The maximum response time after a given control signal is turned ON to operate the ROBO Cylinder using the
PLC’s sequence program, until a response (status) signal is turned, is expressed by the formula below:

Maximum response time (msec) = Yt + Xt + 2 + Command processing time (operation time, etc.)

Yt: Master station

o slave station transmission delay time

Xt: Slave station

o master station delay time



For the master station

o slave station transmission delay time (Yt) and slave station o master station delay time

(Xt), refer to the operation manuals for the PROFIBUS-DP master unit and the PLC in which the master unit is
installed.

















Field network transmission delay time

Command

processing time

PLC sequence program

Control signal

Status signal

SCON-CA

Control signal

Status signal

Master station

o slave

station transmission
delay time (Yt)

Slave station

o master

station delay time (Xt)

This manual is related to the following products: