Tokheim premier b (422b) – Franklin Fueling Systems TS-DTU Data Transfer Unit Dispenser Retrofit Manual User Manual
Page 16
16
Tokheim Premier B DTU Installation
Tokheim Premier B (422B)
This section illustrates the basic components needed
to retrofi t a TS-DTU module into an existing dispenser.
This system can be installed in any “Non-Vapor or Vapor
Ready” dispenser including dispensers with existing
“Balance” or “VacAssist” piping.
Note: Conduit knockouts measure 1 1/4”. Holes are too
small for conduits to make a good seal. These
knockouts cannot be used. New conduit knockouts
will need to be made.
1. Open right options door with key on Side A of
dispenser. Side A has manufacturer’s nameplate.
Remove door and set aside for future installation.
Figure 1: Unlocking door
2. Open printer door on B side of dispenser.
Figure 2: Unlock Printer Door
3. Unlock right options door on B side of dispenser.
Figure 3: Release Latch
4. Release latch on display cover on B side of
dispenser.
Figure 4: Lower Display Assembly
5. Loosen two screws on display assembly and
lower it.
6. Remove lower hydraulics door from side A of
dispenser by releasing key lock on either side of
door.
7. From side A of dispensers, examine opening on
right side of electrical enclosure. Choose drilling
location ensuring that components in electrical
enclosure and hydraulics enclosure will not be
disturbed by the drilling. Use washer to insure
proper clearance after install.
Figure 5; Mark Drilling Location
8. Using a low speed pneumatic drill, drill a small
pilot hole through the bottom of the electrical
enclosure.
Note: During drilling, put a catch pan under the drilling
location to catch shavings and metal fi ling during
drilling operation.
9. Carefully remove all metal fi ling and shavings from
inside of electrical enclosure.