Gas Rating Conversion of Master Burner 1

You must convert Burner 1 (Master) first, and then convert each additional burner in the unit
afterward. Refer to Figures 2-4 and 2-6 to locate Burner 1 (Master) and then perform the
following steps:

1. Turn OFF power to the unit.

2. Gain access to the Factory Menu as follows: press and hold, at the same time, both the

RESET and

buttons while turning ON unit power. Display will enter the Factory

Menu (parameters 3000).

3. Using push buttons

and

select parameter 3002.

4. Press RESET button once to select displayed parameter. Parameter 3002 will begin to blink

in the display. Now the value can be changed using the

and

buttons.

5. Using Table 3-5, select the right parameter value for the unit you are converting to propane

gas or to natural gas.

Table 3-5: Natural Gas and Propane Gas Settings

6. Press RESET button once to save the new value.

7. Turn the power OFF to the unit.

8. Close the manual gas shut off valve.

9. Remove the covers from the unit.

10. Unscrew nut “H” as per Figure 3-42.

11. Using a screwdriver, remove spring clip “A” (Figure 3-42);

12. Remove the gas valve from its site “C” as per Figure 3-43 (note O-ring “L”).

13. Replace orifice “G” per Figure 3-44, for the correct one for type of gas used. Verify that the

stamping on the orifice matches Table 3-5.

14. Reinstall the gas valve, taking care to properly position O-ring “L” in Figure 3-43 and to

place the gasket between the gas valve and nut “H” in Figure 3-42.

15. Open the manual gas shut off valve.