3.16.5.14 Sidewall Termination – Concentric Vent

A concentric vent termination must terminate outside the structure and must be installed as
shown in Figure 3-34. The termination opening must be protected from rain, see Figure 3-35.

Figure 3-34: Concentric Sidewall Termination Clearances