beautypg.com

18 determining location of vertical termination, Am series boilers and water heaters – AERCO AM Series Boiler User Manual User Manual

Page 76

background image

AM Series Boilers and Water Heaters

CHAPTER 3 – INSTALLATION

Page 76 of 156

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0100_0B

PRI - 07/14/14

Ph.: 800-526-0288

GF-146

3.16.5.18 Determining Location of Vertical Termination

Locate the vertical vent/air terminations using the following guidelines:

1. The total length of piping for vent or air must not exceed the limits given in the Section

3.16.3.

2. The vent must terminate at least 3 feet above the highest place in which the vent

penetrates the roof and at least 2 feet above any part of a building within 10 horizontal
feet.

3. The vent must terminate in a tee or acceptable rain-cap.

4. The air piping must terminate in a down-turned 180° return pipe no further than 2 feet

from the center of the vent pipe. This placement avoids recirculation of flue products into
the combustion air stream

5. The vent piping must terminate at least 1 foot above the air intake. The air inlet pipe and

vent pipe can be located in any desired position on the roof, but must always be no
further than 2 feet apart and with the vent termination at least 1 foot above the air intake.

6. Locate terminations so they are not likely to be damaged by foreign objects, such as

stones or balls, or subject to buildup of leaves or sediment.

Figure 3-37: Vertical Vent Termination