3.16.5.21 Installing Multiple Vent and Air Vertical Terminations

Install multiple vent and air terminations in a roof as follows:

Installing Vertical Multiple Vent and Air Roof Terminations

1. When terminating multiple units, terminate each vent/air connection as shown in Figure 3-

38.

2. Place roof penetrations to obtain minimum clearance of 12 inches between edge of air

intake elbow and adjacent vent pipe of another appliance for U.S. installations

3. The air inlet is part of a direct vent connection. It is not classified as a forced air intake with

regard to spacing from adjacent appliance vents.

Figure 3-38: Installing Multiple Vent and Air Vertical Terminations – Two

Alternatives