Start up and operation, 1 overview, 2 critical parameters – Pulsafeeder MPC Vector User Manual
Page 18
12
6. Start Up and Operation
6.1 Overview
Once all electrical connections have been made, your MPC VECTOR is ready for setup and operation. The
following sections detail the procedures required to complete the MPC VECTOR start up.
W
HEN POWER IS SUPPLIED TO THE UNIT
,
LINE VOLTAGE IS PRESENT WITHIN THE
MPC
VECTOR
ENCLOSURE EVEN WHEN THE
M
OTOR IS
OFF.
D
URING
S
TART
-
UP
,
IT IS NECESSARY TO RUN THE PUMP MOTOR
.
T
HIS WILL CAUSE FLUID TO
DISCHARGE FROM THE PUMP
.
Y
OU ARE RESPONSIBLE FOR SAFELY DIVERTING FLOW FROM THE
PUMP DURING START
-
UP AND CALIBRATION
.
6.2 Critical Parameters
For proper operation of the MPC VECTOR control, at startup the following parameters and calibrations must
be entered and/or verified:
Parameter(s)
Reference IOM Section
Pump maximum flow
Section 6.6
Flow meter calibration (if using this feature)
Ref flowmeter IOM as required
Flow calibration in speed mode
Section 8.2
Motor calibration for Vector mode
Section 10
4-20 mA analog signal calibration
Section 8.3
Flow meter type setup
Section 9