Appendix B LRS-PS-FEED Power Supply
LRS-24 Installation and Operation Manual
B-4
Installation and Operation
B.4 Installation and Operation
Preparation for Installation
LRS-PS-FEED can be installed in ETSI racks with front-side access for cable
connection, as well as in ANSI racks, which require rear access. The adaptation is
made by installing the brackets supplied with the unit in the position
corresponding to the desired installation position.
Figure B-4 shows how to install the brackets for front-panel access. Figure B-5
shows bracket installation for rear-panel access.
For installation above the LRS-24, install the brackets as shown in Figure B-4.
Figure B-4. Installation of Brackets for Front Panel Access
Figure B-5. Installation of Brackets for Rear Panel Access