Chapter 2 Installation and Setup

LRS-24 Installation and Operation Manual

2-28

Initial Operation and Basic Checks

I/O Module(s): Refer to the Installation and Operation Manual of the I/O

modules.

If LRS-24 does not show normal indications, see Chapter 5, Troubleshooting and
Diagnostics.

Power Off

To turn off LRS-24 (CM-1):
1. If an external phantom feed voltage source is connected to LRS-24, turn off

that source (for example, the LRS-PS-FEED).

2. Set the ON/OFF switch(es) of the PS module(s) to OFF.
3. Disconnect the DC power, if applicable.

Troubleshooting

If a malfunction occurs in one or more of the links served by a module installed in
LRS-24, perform the following preliminary checks:
• If the problem affects all the links:

− Check that all the indicators on the panels of the PS modules are green.
− If any indicator is red, replace the corresponding PS module.

• Check that all the modules are properly installed.
• Check that all the cable connections are made in accordance with the

installation plan.

• Check that all the communication equipment on the link is operating properly.
• Check for proper configuration of the local and remote equipment.

If these checks do not correct the problem, use a supervision terminal connected
to the MANAGEMENT RS-232 port of the CM-1 module to identify the fault and
replace the corresponding module, see Chapter 5, Troubleshooting and
Diagnostics
.

LRS-24 with CM-2 Module

Power On

To turn on LRS-24 (CM-2):
1. Set the ON/OFF switches on the panels of the LRSI-PSP** modules to ON.
2. Supply the DC power, if applicable.

To supply external phantom feed voltages:
1. Turn on LRS-24.
2. Turn on the source, i.e. LRS-PS-FEED.

Order from: Cutter Networks

Ph:727-398-5252/Fax:727-397-9610

www.bestdatasource.com