[1] Control of Outdoor Unit

[1]- 1 PURY-P400·500 YMF-C

(1)

Initial processing

• When turning on power source, initial processing of microcomputer is given top priority.

• During initial processing, control processing corresponding to operation signal is suspended. The control processing

is resumed after initial processing is completed. (Initial processing: Data processing in microcomputer and initial

setting of each LEV opening, requiring approx. 3 minutes at the maximum.)

(2)

Control at staring

• For 3 minutes after starting, 60 Hz is the upper frequency limit. (When only No. 1 compressor is operating.)

• 75 Hz is the upper limit within 2 hours after the power supply has been turned ON and for the 30 minutes after the

compressor has started operation.

• Normal control is performed after the initial start mode (described later) has been completed.

(3)

Compressor capacity control

• Variable capacitor compressor is performed by the variable capacity compressor (No. 1: inverter motor) and

constant capacity compressor (No. 2: It has capacity control switching).

• In response to the required performance, the number of compressors operating, the switching of capacity control

and the frequency of the variable capacitor compressor is controlled so that the evaporation temperature is

between – 2 and – 6

°

C in cooling mode and that the condensation temperature is 49

°

C in heating mode.

• The fluctuation of the frequency of the variable capacitor compressor is as follows. It is performed at 2 Hz per

second.

20 to 100 Hz (TH6 > 20

°

C and in cooling mode, or in heating mode)

30 to 100 Hz (TH6 < 20

°

C and in cooling mode)

1) No. 2 compressor operation, stopping and full-load/un-load switching

1

Switching from stopping to operation of No. 2 compressor.

When the required performance cannot be obtained by only No. 1 compressor, the No. 2 compressor will be

started. (The No. 2 compressor will be started in un-load operation.)

• After the No. 1 compressor has reached 100 Hz, the No. 2 compressor stops

un-load or un-load

full-load.

2

Switching from operation to stopping of No. 2 compressor.

When the required performance is exceeded when the two compressors, No. 1 and No. 2, are operating, the No.

2 compressor is stopped or performed in un-load operation.

3

Switching from un-load to full-load of No. 2 compressor

When the required performance cannot be obtained by the No. 1 compressor and the No. 2 compressor operat-

ing in un-load, the No. 2 compressor will be switched to full-load operation.

4

Switching from full-load to un-load of No. 2 compressor

When the required performance is exceeded when the two compressors, No.1 and No. 2 operating in full-load,

the No 2 compressor will be switched to un-load operation.

2) Pressure control

The upper limit value for the high pressure (Pd) has been set for each frequency. When this value is exceeded, the

frequency is reduced every 30 seconds.

3) Discharge temperature control

The discharge temperature of the compressor (Td) is monitored during the operation. If the upper limit is exceeded, the

frequency is reduced by 5 Hz.

• Control is performed every 30 seconds after 30 seconds at the compressor starting.