7  Commissioning

SMA Solar Technology AG

44

SSM16-24-IA-IEN105120

Installation Guide

The Sunny String-Monitors are not terminated on delivery so that they can be configured as required
on site. The hubs in the Sunny Central are terminated on delivery.

Figure 17: Termination of the data cable (example)

Requirement:

☐ All Sunny String-Monitors on a string are connected to the RS485 bus (see section

6.5.3 ”Connecting the Data Cable in the Sunny String-Monitor”, page 37 and section
6.5.4 ”Connecting the Data Cable in the Sunny Central”, page 38).

1. Plug the jumper on the upper String Monitor Unit into

the last Sunny String-Monitor of each string.