Caution

If any odor of gas is detected, or if the gas burner

does not appear to be functioning in a normal

manner, close the main gas shutoff valve.

Do not shut off the power switch. Contact your

heating contractor, gas company, or factory

representative.

10.2.2 Combustion Setup Procedure
See the detailed instructions in Section 9.

WarnInG

Improper adjustment may lead to poor

combustion quality, increasing the amount of

carbon monoxide produced. Excessive carbon

monoxide levels may lead to personal injury or

death.

10.3 Shutting Down the neotherm

Unit

This step must be performed by a qualified
service person.
1. Turn off the main electrical disconnect switch.
2. Close all manual gas valves.
3. If freezing is anticipated, drain the NeoTherm

and be sure to also protect the building piping

from freezing. All water must be removed

from the heat exchanger or damage from

freezing may occur.

10.4 restarting the neotherm Unit

If the system has been drained, see Section 10.1 for

instructions on proper filling and purging.
1. Turn off the main electrical disconnect switch.
2. Close all manual gas valves.
3. Wait five minutes.
4. Set the aquastat or thermostat to its lowest

setting.

5. Open all manual gas valves.
6. Reset all safety switches (pressure switch,

manual reset high limit, etc.).

7. Set the temperature controller to the desired

temperature setting and switch on the electrical

power.

8. Each burner will go through a prepurge period

and ignitor warm-up period, followed by

ignition.

10.2 Initial operation

The initial setup must be checked before the unit is

put into operation. Problems such as failure to start,

rough ignition, strong exhaust odors, etc. can be due

to improper setup. Damage to the boiler resulting

from improper setup is not covered by the limited

warranty.

10.2.1 Initial Burner operation
1. Using this manual, make sure the installation

is complete and in full compliance with the

instructions and all local codes.

2. Determine that the unit and system are filled

with water and all air has been bled from both.

Open all valves.

3. Observe all warnings on the Operating

Instructions label and turn on gas and electrical

power to the unit.

4. The NeoTherm unit will enter the start

sequence. The blower and pump will energize

for pre-purge, then the ignition sequence will

start. After all safety devices are verified, the

gas valve will open. If ignition doesn’t occur,

turn off the NeoTherm. Check that there is

proper supply of gas. Wait five minutes and

start the unit again.

5. If ignition starts normally, leave the NeoTherm

unit turned on.

6. After placing the unit in operation, the Burner

Safety Shutoff Device must be tested:

(a) Close the gas shutoff valve with the

burner operating.

(b) The flame will go out, and the blower will

continue to run for the post purge cycle.

A few additional attempts to light will

follow including pre-purge, ignitor on,

valve/flame on and post purge. Ignition

will not occur because the gas is turned

off. The ignition control will lockout.

(c) Open the gas shutoff valve. Reset the

boiler control by pressing the Reset

button on the control. Restart the

appliance. The ignition sequence will

start again and the burner will start. The

appliance will return to its previous mode

of operation.