Control technology | ethercat communication manual – Lenze EtherCAT control technology User Manual
Page 44

Control technology | EtherCAT communication manual
Commissioning of the system
Overview of commissioning steps
44
L
DMS 3.1 EN 01/2011 TD17
The main commissioning steps are listed in the following table:
Step
Activity
Software used
1.
2.
3.
Fieldbus scan with the »EtherCAT Configurator«
»EtherCAT Configurator«
Fieldbus scan with the »scandf« command line tool ( 51)
Command line tool »scandf«
4.
Inserting devices available on the fieldbus into the »EtherCAT
»EtherCAT Configurator«
Creating the configuration in the »EtherCAT Configurator«
5.
Export of EtherCAT configuration
»EtherCAT Configurator«
6.
Configuration in the »Engineer«
»Engineer«
8.
Configuration in the »PLC Designer« ( 68)
»PLC Designer«
9.
Loading the control configuration onto the IPC ( 78)
»PLC Designer«
10.
Loading the master configuration onto the EtherCAT master ( 79)
»PLC Designer«
11.
Loading and starting the PLC program ( 79)
»PLC Designer«