Completing the Installation

It’s a good idea to look over the entire installation before applying power to the enclosure.

Clean out dust and debris from the enclosure interior.

Check for loose connections, bare wires, and damaged insulation. Repair any damage
that is discovered.

Check Main Power Wiring

Check resistance between line, neutral, and ground busses with a digital voltmeter (DVM).

Line to ground resistance should be 10M Ohm or higher.

Neutral to ground resistance should be 0 Ohm.

Line to neutral resistance should be 10M Ohm or higher.

Re-install the rack power supply into the top slot of the ERn enclosure.

Check Line Voltages

Check the voltage on your input terminals using a digital volt meter (DVM) before installing

modules.

HIGH LEAKAGE CURRENT

Ground connection is essential before connecting supply

Disconnect power before removing modules

Service by authorized persons only.

Step 1:

Close the ERn door.

Step 2:

Apply line power at the main circuit breaker for 90 seconds. Observe the

enclosure for evidence of shorting, like arcing sounds or a burning smell. If you

detect evidence of shorting, shut off power and fix the wiring.

W A R N I N G :

Power must be turned OFF when you perform this procedure. ETC

recommends that your facility adopts a lockout / tagout procedure to protect

your maintenance personnel during maintenance procedures.

W A R N I N G :

Line voltages will be on the input terminals during this procedure. You must

be a qualified electrician familiar with the hazards of working with high

voltage electricity. Use extreme caution when performing this procedure.

ERn door removed from graphic for

clarity of rack power Supply

installation.