Install Rack Enclosures

13

Rough-in Conduit and Wiring

Remove Option Modules

Prior to installing conduit and pulling wires into the ERn enclosure, remove the rack power

Supply (top of enclosure) and blank option module (bottom of enclosure) from the ERn

enclosure to provide a clear access to the conduit access openings and connections.

Step 1:

Loosen the two captured thumbscrews that secure the Rack Power Supply to the

ERn enclosure.

Step 2:

Pull the power supply straight out of the rack.

Step 3:

Repeat for the blank option module, Ethernet Switch or secondary power supply.

Step 4:

Place these modules in a safe place until the conduit rough-in and wiring

terminations are complete.

W A R N I N G :

All rack terminations must be done with the power off. Racks installed

without an accessible power disconnect device cannot be serviced or

operated safely. Follow all local codes and restrictions.
When the disconnect device is not located near the installed rack enclosure,

the disconnect should allow for proper lockout / tagout.

See “Lockout /

Tagout” on page 6.

N o t e :

For 230 VAC CE enclosures, before removing any modules, loosen the hardware

and slide the module retention bar to the left.

N o t e :

An ERn4 at 230 VAC does not support the Redundant Rack Power Supply (ERn-

RPS) nor the Ethernet Switch Option Module (ERn-NET). Instead an ERn4 at 230

VAC is shipped from the factory with a Rack Power Supply installed in the top

(normal) position and in the lower option module slot.

Rack power supply (ERn-PS)

The blank option module installed

at shipment can be replaced with

either the Ethernet Switch Module

(ERn-NET) or the Redundant