beautypg.com

Vent termination – Bryant Bruant 4 Way Gas 355AAV User Manual

Page 40

background image

40

11. Horizontal portions of the venting system shall be

supportive to prevent sagging support. Support combustion

air piping (if applicable) and vent piping a minimum of
every 5 ft. (1.5 M)(3 ft. (.91 M) for SDR--21 or --26 PVC)
using perforated metal hanging strap.

12. Slope combustion air piping (if applicable) and vent piping

downward towards furnace a minimum of 1/4 in. (6 mm)

per linear ft. with no sags between hangers.

13. Horizontal portions of the venting system shall be installed

so as to prevent the accumulation of condensate.

14. Use appropriate methods to seal openings where

combustion air pipe (if applicable) and vent pipe pass

through roof or sidewall.

EXAMPLE

An 100--14 size furnace located in Indianapolis, elevation 650

ft. (198 M) above sea level, could be installed as either a direct

vent/2--pipe system that requires 3 elbows and 28 ft. (8.5 M)

of vent pipe, along with 5 elbows and 34 ft. (10.3 M) of

combustion--air pipe OR a non--direct vent/1--pipe system that

requires 3 elbows and 28 ft. (8.5 M) vent pipe.

For a direct vent/2--pipe system, Table 11 indicates this

application would allow a 2--in. (51 mm) diameter vent pipe,

but require a 2--1/2 in. (64 mm) diameter combustion air pipe.

According to Table 11, 2--in. (51 mm) diameter pipe is good

for 30 ft. (9.1 M) with 3 elbows, but only 20 ft. (6.1 M) with 5

elbows. Therefore, 2--1/2 in. (64 mm) diameter pipe must be

used for both vent and combustion air pipes since larger

required diameter must always be used for both pipes.

For a non--direct vent/1--pipe system, Table 11 indicates that

this application would allow a 2--in. (51 mm) diameter vent

pipe. If same installations were in Albuquerque, elevation

5250 ft. (1600 M) above sea level:

For a direct vent/2--pipe system, Table 11 indicates that 2--1/2

in. (64 mm) diameter vent pipe and combustion--air pipe are

required.

For a non--direct vent/1--pipe system, Table 11 indicates that

2--1/2--in. (64 mm) diameter vent pipe is required. If same

applications are to be installed at 5001-- to 6000 ft. (1524 --

1829 M) elevation:

For a direct vent/2--pipe system, 2--in. (51 mm) pipe is only

good for 23 ft. (7.0 M) (with 3 elbows) and 13 ft. (3.9 M)

(with 5 elbows). Therefore, 2--1/2 in. (64 mm) diameter

combustion air and vent pipe must be used.

For a non--direct vent/1--pipe system, a 2--in. (51 mm)

diameter pipe is only good for 23 ft. (7.0 M) with 3 elbows. A

2--1/2--in. (64 mm) diameter vent pipe must be used.

VENT TERMINATION

General

Combustion--air (direct vent/2--pipe system only) and vent pipe

must terminate outside structure, either through sidewall or roof.
For vent termination clearance, refer to Table 8 for Direct

Vent/2--Pipe system and Table 9 for Non--direct Vent/1--Pipe
system. For exterior piping arrangements, refer to Fig. 43 for

Direct Vent/2--Pipe system and Fig. 44 for Non--Direct/1--Pipe

system.
Roof termination is preferred since it is less susceptible to damage

or contamination, and it has less visible vent vapors. Sidewall
termination require sealing or shielding of building surfaces with a

corrosive resistance material due to corrosive combustion products
of vent system.
NOTE: (Direct Vent/2--Pipe system ONLY) A factory accessory
termination kit MUST be used. See section “Vent Termination Kit
(Direct Vent/2--Pipe System Only)” in this instruction.
When determining appropriate location for termination, consider

the following guidelines:

1. Comply with all clearance requirements stated in Table 8 or

Table 9 per application.

2. Termination or termination kit should be positioned where

vent vapors will not damage plants/shrubs or air
conditioning equipment.

3. Termination or termination kit should be positioned so that

it will not be affected by wind eddy, such as inside building

corners, nor by recirculation of flue gases, airborne leaves,
or light snow.

4. Termination or termination kit should be positioned where it

will not be damaged by or subjected to foreign objects such
as stones, balls, etc.

5. Termination or termination kit should be positioned where

vent vapors are not objectionable.

Extended Exposed Sidewall Pipes

Sidewall combustion air pipe termination (direct vent/2--pipe
system only) and vent pipe termination may be extended beyond

area shown in Fig. 43 or in Fig. 44 per application in outside
ambient by insulating pipe as indicated in Table 10.

1. Determine combustion air pipe diameter (direct vent/2--pipe

system only) and vent pipe diameter, as stated above, using

total pipe length and number of elbows.

2. Using winter design temperature (used in load calculations),

find appropriate temperature for your application and
furnace model.

3. Determine required insulation thickness for exposed pipe

length(s).

NOTE: Pipe length (ft. / M) specified for maximum pipe lengths
located in unconditioned spaces cannot exceed total allowable pipe
length as specified in Table 11.

Vent Termination Kit (Direct Vent/2--Pipe System

Only)

NOTE: Always refer to the instructions in termination kit for the
latest version.
Combustion air and vent pipes MUST terminate outside structure.

A factory accessory termination kit must be installed as shown in

Table 12. There are four options of vent/combustion air
termination kits available as shown in Table 12.
NOTE: Combustion air pipe must have the same diameter as vent
pipe.

Concentric Vent/Combustion Air Termination Kit

(Direct Vent/ 2--Pipe System Only)

Determine an appropriate location for termination kit using the
guidelines provided in section “Vent Termination: General” in this

instruction.

1. Cut one 4--in. (102 mm) diameter hole for 2--in. (51 mm)

kit, or one 5--in. (125 mm) diameter hole for 3--in. (76 mm)
kit.

2. Loosely

assemble

concentric

vent/combustion

air

termination components together using instructions in kit.

3. Slide assembled kit with rain shield REMOVED through

hole.

NOTE: Do not allow insulation or other materials to accumulate
inside of pipe assembly when installing it through hole.
Roof terminations–Locate assembly through roof to appropriate

height as shown in Fig. 43.
Sidewall terminations--Locate assembly through sidewall with

rain shield positioned no more than 1--in. (25 mm) from wall as
shown in Fig. 43.

4. Disassemble loose pipe fittings. Clean and cement using

same procedures as used for system piping.

5. Check required dimensions as shown in Fig. 43.

355A