Receipt of goods and storage, Preparation and installation, Figure 1 – M&C TechGroup SP2000-H320_S2 Operator's manual User Manual

Page 11: Probe construction eg. version sp2000-h320/s1, 10 receipt of goods and storage, N o t e, 11 preparation and installation

background image

11

Gas sampling and gas conditioning technology

2-1.1.4-ME

1

2

5

4

3

6

Figure 1 Probe construction eg. version SP2000-H320/S1



10

RECEIPT OF GOODS AND STORAGE

The gas sample probe and any special accessories should be removed carefully from the packag-

ing and checked immediately for completeness against the delivery note;

Check the goods for any damage incurred during transport and if necessary inform your transport

insurer of any damage.


The gas sample probe is normally delivered in two packaging units:

1. The gas sample probe with the screws, nuts and flange seal required for mounting;

2. Sample tube or pre-filter, if applicable with extension tube.

N O T E !


The equipment should be stored in a protected, frost-free room!



11

PREPARATION AND INSTALLATION

Select the optimal sampling point in accordance with the generally applicable guidelines of

consult the competent persons.