Task 001: Pre-Installation Checklist

Before installing the BitStorm 1900 system, verify that the following
steps have been completed:

Step

Procedure

1.)

Perform site survey and verify equipment bays are installed

correctly.

2.)

Verify that the amount of rack space is adequate for the required

installed application.

3.)

Verify the racks are secured and electrically grounded according to

standard industry practice. Refer to "Appendix A. Installation
Requirements," on page 107
for specifications.

4.)

Verify you have all necessary tools, equipment, and materials for

the installation. Use the following table as a guide

Table 2-8: Installation Tools, Equipment, and Materials

Tools, Equipment, and Materials

Installation hardware kit supplied with shelf

Phillips-head screwdriver (#1 or #2)

Anti-static protection such as a grounded wrist strap

Volt-ohm meter

PC with serial port to configure MIU

Cross-connect punch-down tool

14-gauge stranded cable

Cable ties

5 BitStorm 1900 cable harnesses

5 intermediate cables

Cross-connect block(s) of the same type used in the existing main distribution
frame (MDF)

24 AWG Jumper Wires (24 wires per modem card)