DBK34A Block Diagram

Hardware Setup

Configuration for 12 Volt (Default) or 24 Volt Operation

DBK34A’s Screw Terminal Board, TB1

DBK34A’s screw terminal numbers read from right to left (9,8,7…3,2,1) when viewed from the front

panel (see figure).

For 12 Volt Operation:

1. Remove jumper from terminals 8 and 7, if present.

2. Use a jumper to short terminals 9 and 8

3. Use a jumper to short terminals 7 and 6

For 24 Volt Operation:

1. Remove jumpers from terminals 9 and 8, if present

2. Remove jumpers from terminals 7 and 6, if present.

3. Use a jumper to short terminals 8 and 7.

Power

Power In (12 or 24 VDC only).

Connect MAIN POWER INPUT (+) positive to Terminal 3 of TB1.

Connect MAIN POWER INPUT (-) negative to Terminal 5 of TB1.

TB1’s Terminal 4 is reserved for factory use and is not to be connected by the user.

The use of an optional auxiliary battery will extend run-time. For use with DBK34A,

auxiliary batteries must be of lead-acid chemistry, in the 2 to 3 A-Hr range, and of the same

voltage as that set by the Voltage Select Jumpers. Auxiliary batteries charge and discharge in

the same manner as the internal batteries. If an auxiliary battery is to be used, connect AUX

BATT (+) positive to Terminal 1 (of TB1), and connect AUX BATT (-) negative to Terminal

2 (of TB1).