Connecting Your 1394 SERCOS Interface System

3-17

Wiring Logic Power

To wire the logic power connector:

1. Prepare the incoming 24V dc logic power wires for attachment to

the logic power connector by removing 10 mm (0.375 in.) of
insulation.

2. Route the 24V dc power wires (W1 and W2) to your 1394 system

module.

3. Insert the incoming 24V dc logic power wires into the logic power

connector plug as follows and tighten the connector plug screws.

4. Gently pull on each wire to make sure it does not come out of its

terminal. Re-insert and tighten any loose wires.

5. Insert the logic power connector plug into the logic power

connector on the bottom of the system module (refer to Figure 2.1
for the connector location).

6. Go to Connecting Motor Power, Thermal Switch, and Brake.

Connecting Power Wiring for 22 kW System Modules

The 1394C-SJT22-D system module use IEC terminal blocks instead of
connectors for making power connections. You will wire the system
module using the power terminal blocks. Refer to Figure 2.2 for the
terminal block location.

IMPORTANT

Use caution not to nick, cut, or otherwise
damage strands as you remove the insulation.

Insert the wires labeled:

Into the connector terminals
labeled:

W1

W1

W2

W2

ATTENTION

!

To avoid personal injury and/or equipment damage,
ensure installation complies with specifications
regarding wire types, conductor sizes, branch circuit
protection, and disconnect devices. The National
Electrical Code (NEC) and local codes outline
provisions for safely installing electrical equipment.