beautypg.com

Det-Tronics UD10 DCU Emulator FlexVu Universal Display Unit User Manual

Page 60

background image

4.2

95-8656

L-3

instAllAtion

wIRINg REQUIREmENTS
The simplest installation involves installing the sensor

into one of the UD10-DCU openings and connecting

the wiring directly to the CGS interface board.

Sensor Separation
If the installation requires separation of the CGS

sensor and the UD10-DCU Display, the sensor can be

connected to a model STB1 sensor termination box,

and the CGS/STB combination wired to the UD10.

In this case, shielded cable is recommended to help

protect against interference caused by extraneous

electrical “noise.”

In applications where the cable is installed in conduit,

the conduit should not be used for wiring to other

electrical equipment whenever possible. If other

equipment power wiring is run in the same conduit, the

cabling must be shielded.

The maximum allowable distance between the CGS

sensor and UD10-DCU Display Unit is 500 feet, with

connecting cable 16 AWG minimum.

INSTaLLaTION aND wIRINg PROCEDURE
1. Determine the best mounting locations for the

detectors.

2. Install the CGS sensor within the proper opening

in the UD10-DCU or STB junction box. Mount the

device with the sensor oriented vertically and the

opening pointing down. All junction boxes should

be electrically connected to earth ground.

3. Terminate all wiring at the proper terminals. Refer to

the appropriate illustration for details.

4. Double check that all wiring is the proper size and

type and has been installed correctly. Check for

correct operating voltage at the device.

noTe

Do not apply power to the system with the junction
box cover removed unless the area has been
de-classified.

5. Proceed with startup and calibration.