3: Operating Procedures

19

Flow monitoring

The

FLOW READING screen is the one most used during normal monitoring operation. It shows the instantaneous

fluid flow together with totalized values (when enabled). In this mode you can select the flow rate measurement
units by pressing keys 7 (liters), 8 (Gallons, Barrels) or 9 (m³), or change the display to show velocity by pressing
key 4.

3.4

Managing Named Sites

If you want to monitor a particular site location frequently, you can set up a named ‘Site’ to store the installation
details, such as pipe dimensions and material, required to set-up the PUF system. These can then be recalled
later when revisiting that particular location.

The instrument can store up to 20 sites, the first site is reserved for

QUICK START and cannot be renamed;

subsequent sites are initially named

EmptySite1 through to EmptySite19.

3.4.1 Setting up a new site

18. Check that the indicated signal strength on the

left of the screen is at least 2 bars (ideally 3 or 4).
If less than 2 bars are shown it indicates there
could be a problem with the transducer spacing,
alignment or connections; or it could be due to an
application problem.

FLOW READING

DD-MM-YY HH:MM:SS

Qxx.xx%

Signal

gal/min

+Total: 0.00 gal

–Total: 0.00 gal

Key Point: Once you have set up a named site you are advised to log some data to
the site in order to avoid the possibility of the site name being overwritten when the
QuickStart data is saved. See Paragraph 3.6.3 for details.

1.

Select

View Edit Site Data from the MAIN

MENU.

2.

Select

Choose from list of sites.

3.

Select one of the

EmptySites from the

presented list (e.g.

EmptySite 1 as shown).

4.

Select Site name and press the ENTER key.

VIEW EDIT SITE DATA

DD-MM-YY HH:MM:SS

Choose from list of sites

Site name : EmptySite1

Dimensions : Inches

Pipe outside diameter: 0.00

Pipe wall thickness : 0.00

Pipe lining thickness: 0.00

5.

This opens the ALTER NAME screen.

6.

Select

Alter the Site Name and you will be

presented with a screen which allows you to
enter a new name in much the same way as
when composing a mobile text message.

7.

On completion press the

ENTER key then select

Exit. This will take you back to the VIEW EDIT
SITE DATA screen.

ALTER NAME

DD-MM-YY HH:MM:SS

Site name : EmptySite1

Do you wish to:–

Alter the Site Name

Exit

0.000