FUNCTIONAL TESTING (GENERAL)

NOTE: Before performing any functional testing make

sure the Flame Guardian™ is disconnected to
prevent unwanted discharge. See Wiring
Diagram.

To perform any functional test, the following instruc-
tions should be followed.

1. Ensure that the Flame Guardian™ module(s) is/are

not connected to power source.

2. Perform the desired Functional Test. Sound alarm

will go off.

3. Check fire zone.

4. Press the

SIGNAL SILENCE

button on the

Guardian™ Panel to suppress alarm.

5. Press the

SYSTEM RESET

button.

To proceed with testing:

• Restart procedure.

If testing has been completed:

• Reconnect the Flame Guardian™ module(s).

• Make sure the panel is in RUN mode.

FUNCTIONAL TEST (SOLENOID VALVE)

The solenoid valve is provided with a button for testing
purposes.

1. Press button (A) and check that the compressed air

escapes from outlet R (B). See Figure A.19.

OIL GUARDIAN™ INSTALLATION

See Oil Guardian™ Instruction Manual for detailed
instalation instructions.