16 STARTING

 Before starting up check whether the mains power supply voltage corresponds with the information

stated on the probe's nameplate.

 If there is a built-in ball valve you should also check, if it is closed. In case of hand-operated ball

valves, the control grip must be located at the right-hand stop.

 Switch on mains power supply.

 Check the rated value setting on the built-in thermostat or on the external controller.

 The total heating-up time is approximately 2 hours. After about 1 hour the probe is already suffi-

ciently heated for the temperature to have exceeded the temperature failure alarm value (30°C be-
low rated value), but it still takes about another hour until operating temperature is reached.

 If a ball valve is fitted, operate this via the pneumatic drive or for a 2/2-way ball valve by turning the

control grip by hand up to the left-hand stop and for a 3/2-way ball valve into mid position.

 The probe is ready for operation now.