Running an omr test, En glish – Formax 6404 Series User Manual
Page 87
An Example of OMR Code
In the figure the legend for the following example is shown. In this example, a set of 8
sheets with one selective feed and three sequence check marks is shown.
• The first position is used for the start mark which must be printed on every sheet.
• The second mark position is used for the insert/accumulate command. A printed
mark means insert, no mark means accumulate. Therefore the mark is printed on
the last sheet of the set.
• Position 3 is reserved for selective feed from the enclosure feeder. Print a mark on
position 3 when a selective feed from the enclosure feeder is required. The marks
are printed on the last sheet of the set.
• Position 4, 5 and 6 are used for the sequence check marks. In this case a three mark
sequence check is used.
Running an OMR test
To run an OMR test:
Before running an OMR test, select a job that uses OMR reading.
1.
In the Test menu, press the
[OMR test] button. The OMR test menu appears.
80
| Page 80 | jan-06-2012 13:58 |
7
En
glish