Commissioning
Technical requirements
All components to be monitored must be connected and operating.
The visual display & operating panel must be provided with a CompactFlash
™
card and
the power supply must be switched on.
Start-up behaviour
To commission the display & operating panel switch on the power supply. First a system
test is carried out. Then the hardware is checked.
After that the user program is automatically loaded from the CompactFlash
™
and the start
menu is displayed (duration: approx. 4 min.).
Shutdow n behaviour
A short power supply failure of up to 10ms will be buffered by the power supply unit. In
the event of a longer power failure you have to reset SPECTOR
control
in order to restore
the power supply.
Factory settings
The graphical screen masks are configured by GESTRA. All adjustable masks are
completely available, no matter whether the indicated instruments are part of the bus
system or not. Subsequent expansion or modification is therefore possible at any time.
The scope of the adjusted values and hence the degree of preadjustments depends
whether a pre-configured OEM version is used or whether SPECTOR
control
will be
connected to an existing bus system and therefore the configuration of the system must
be completely new.
If a pre-configured OEM version is used, the individual components with the adjusted
parameters are stored on the CompactFlash
™
card.
Note
Any fault occuring during start-up will be indicated.