beautypg.com

3brewer system setup – Kipp&Zonen Brewer MkIII User Manual

Page 26

background image


MKIII OPERATOR’S MANUAL

23



3

BREWER SYSTEM SETUP


Prior to accepting a shipment from the carrier, the containers should be inspected for
damage. If any dents or major scratches, cuts, etc. are evident, a damage claim should be
filed with the carrier. Only after incoming inspection and operational tests of the Brewer are
successfully completed, should the shipment be accepted.

These instruction lead an installer through the Setup of a Brewer Spectrometer.

Since Brewers are usually operated at some distance from the Computer Equipment, (probably out
of doors, and out of site of the Computer room), the setup will be done in two stages. The Brewer
will first be set up and tested in close proximity to the Computer, and then it will be installed at its
final location.

Before starting, ensure that correct AC voltage is availabe as per the diagram in Figure 3.1 and
Table 3.1.












Figure 3.1: AC Power Voltages


Table 3.1

AC Power Connector Voltages

measured voltages between

230VAC installations

120VAC installations

ground & neutral

0 VAC

0 VAC

ground & hot

240 VAC

120 VAC

neutral & hot

240 VAC

120 VAC



REFER TO FIGURES 3.2 and 3.3 FOR THE FOLLOWING SETUP

The complete Brewer Spectrometer system consists of the following:

a Spectrophotometer

an Azimuth Tracker

a Tripod Stand

a Control and Data Logging Computer (optionally from KIPP & ZONEN)

a set of Interconnect Cables

a set of Basic Spare Parts

a set of Optional Spare Parts

other Optional parts

3. BREWER SYSTEM SETUP