beautypg.com

Chapter 15 check-out procedures – AERCO Esteem O&M Manual User Manual

Page 66

background image

60

N

OTICE

Perform the following check-out proce-
dures as outlined and check off items as
completed. When procedures are com-
pleted, the installer should complete the
installation record on page 61.

Check-Out Procedures

Boiler system water chemistry checked
and verifi ed as outlined on page 39.

The boiler air vent and any automatic air
vents placed within the system are open
one full turn.

Air is purged from the heating zones and
boiler system piping.

Confi rm that the burner is properly confi g-
ured for the fuel supply.

• Natural

Gas—page

30

• Propane—page

31.

Thermostat circuit wiring checked and
verifi ed that no voltage is present to the
low voltage terminals as outlined on page
41.

Operating Instructions on page 47 were fol-
lowed during start-up.

Combustion levels and fl ame pattern veri-
fi ed as outlined on page 43.

Measured the rate of input on Natural
Gas as outlined on page 44.

Checked the incoming gas pressure to
the Esteem 399 Low NOx to ensure a
minimum pressure of 5”w.c during fl ow
conditions to all gas appliances and a
maximum pressure of 13”w.c during non-
fl ow conditions for Natural and Propane.

Adjusted balancing valves and system
limit controls to provide design tempera-
tures to the primary space heating sys-
tem.

In multiple zone applications, adjusted for
correct fl ow of boiler water to each zone.

Checked and verifi ed room thermostat(s)
function properly and the thermostat(s)

heat anticipator (if used) was properly set.

Observed several operating cycles for
proper operation of the Esteem 399 Low
NOx and the system.

Set the room thermostat(s) to the desired
room temperature.

Reviewed all instructions shipped with the
Esteem 399 Low NOx with the homeown-
er or maintenance personnel.

Completed the Installation Record on
page 61.

Ensure all manuals and other documents
are returned to the Installation envelope
and given to the owner for safekeeping.

Chapter 15

Check-Out Procedures

GF-125