Commissioning

6.1

Before initial switch-on

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

6

Commissioning

During commissioning, plant-specific data such as motor parameters, operating parameters,

responses, and parameters for fieldbus communication are defined for the inverter. Lenze devices

use codes for this purpose.
The codes of the inverter and for communication are saved to the memory module in a non-volatile

data set.
In addition, there are codes for diagnosing and monitoring the stations.

Parameters of the communication module

( 97)

6.1

Before initial switch-on

Stop!

Before you switch on the Inverter Drive 8400 and the communication module for the

first time, check the entire wiring for completeness, short circuit and earth fault.