Part No. 4801-5120 Rev. 6-09
Mega-Cool System
Page 7
Installation Cross-Section (Systems 10
'
to 120
'
)
NOTE: 2x6 refers to U. S. finished
lumber measurements.
Framing Diagram For 10' To 120 Ft. Center-Mount Systems
Splash Guard
Minimum Clearance
6 inches from roof
Cover
Back-Plate
Support Bracket
Drip Rail
8” Pipe
Support
Bracket
2" x 6" Board or Equivalent
or Steel Equivalent. See Page 5.
BackPlate
Post
Pad
(End-Cap
not shown)
"A"
Pad Heig
ht
Bottom
Flashing
12"(30.5 cm) for 4" pad
11"(27.9 cm) for 6" pad
"B"
9.5" (24.1 cm) Minimum
Rou
gh Op
eni
ng
"C"
1. Drawing shown to the right is an overview of
a completed Mega Cool Center-Mounted Pump
System without the left end cap.
2. The figure details the overall dimensions for
each pad system and minimum clearance from
roof.
Dimension ("A")
(6” PAD)
(4” PAD)
4 ft Pad
61 1/8 in.
155.23 cm
62 1/8 in.
157.80 cm
5ft Pad
73 1/8 in.
185.74 cm
74 1/8 in.
188.23 cm
6ft Pad
85 1/8 in.
216.22 cm
86 1/8 in.
218.76 cm
Rough Opening Dimension ("B")
(6” PAD)
(4” PAD)
4 ft Pad
49 1/8 in.
124.78 cm
50 1/8 in.
127.32 cm
5ft Pad
61 1/8 in.
155.26 cm
62 1/8 in.
157.80 cm
6ft Pad
73 1/8 in.
185.74 cm
74 1/8 in.
188.23 cm
Dimension ("C")
(6” PAD)
(4” PAD)
4 ft Pad
50 1/8 in.
127.32 cm
51 1/8 in.
129.85 cm
5ft Pad
62 1/8 in.
157.80 cm
63 1/8 in.
160.34 cm
6ft Pad
74 1/8 in.
188.28 cm
75 1/8 in.
190.82 cm
Splash Guard
Support Bracket
Shown with In-Line
Pump Option
Framing Diagram
Note: Air Flow
up behind
Back Plate
between
posts.
Post
Back-
Plate
Support
Bracket
6
Overall