OPERATOR’S MANUAL
IntelliAg MVT
11001-1643-201401
52 / VEHICLE PREPARATION
TEST GROUND SPEED
Test Ground Speed is the ground speed reference used to perform the test.
ROW
Row is the active row viewed on the system. The row that is set here is the
row that reports back a seed count in the Test Seed Count value. The
operator can change the row # to get performance of all rows during the
Continuous Test to see row-to-row variability.
TEST TARGET POPULATION
Test Target Pop is the seed rate at which the test is performed. This value
is the current target rate and is automatically populated.
TEST SEED COUNT
NOTE:
The Test Seed Count will
automatically reset whenever a
new Continuous Test is
performed.
Test Seed Count is the seed count reported back on the specified row set in
the row data item and is automatically populated.
5 REV TEST
5 Rev Test checks the seed meters for accuracy. When started, the test
runs the control for five revolutions of the seed meters then shuts down.
The seed count can then be correlated on a row versus the seed count
actually dispensed by the meter. A remote test switch is recommended to
perform this test.The values entered do not affect any other setup values
that have previously been tested.
To Perform the 5 Rev Test:
1. Press the Controls button.
2. Press the 5 Rev Test button.
3. The following parameters must be entered to perform a 5 Rev Test.
– Test Ground Speed
– Row
4. Press the Start button. The test runs for 5 revolutions then stops.
Figure 47