beautypg.com

Recommended cable installation, Figure 3-2 cable installation methods – RLE LD5000 User Manual

Page 18

background image

Chapter 3: Installation

User Guide: LD5000

10 970.484.6510

www.rletech.com

• If the cable is installed over an obstruction, clip the cable on both sides, as close to the obstruction

as possible.

• Do not install the cable directly in front of an air conditioner. Allow a minimum of six feet

between the unit and the cable. If the cable is too close to the air conditioning unit’s air stream, the
moisture from the humidifier may cause false leak readings. If the cable must be installed in front
of an air conditioning unit, place the J-clips 12 to 18 inches apart.

3-2.1.1 Recommended Cable Installation

Figure 3-2 Cable Installation Methods


Laid freely on the floor.

Only recommended in

spaces with no access.

Secured to floor with mastic.

Installed in protective covering.

Secured to floor with J-clips.

Secured to floor with tie wrap.

Secured to pedestal with tie wrap.

Do Not Secure as Shown

NOTE:

It is important to finish the end of the leak detection cable with the end
terminator. If the end terminator is not present, a cable fault will register.

Note any variances between the cable layout diagram and the actual cable
installation.