beautypg.com

REMKO Multi-talent User Manual

Page 33

background image

Designation

Value range

Factory setting

Description

WE Dyn up

20-500

350

Setting the value for the connection of all heat generator-
levels
(WE-connection dynamic [K]).

If the cumulative system deviation in Kelvin reaches the
value set here, this effects the connection of all
heat generator-levels (the smaller the value, the faster the
connection).

Values which are too low can lead to the clocking of heat
generator.

WE Dyn down

20-500

20

Setting the value for the shut-off of all heat generators
(WE-shut-off dynamic).

If the cumulative system deviation in Kelvin reaches the
value set here, this effects the shut-off of all heat generators
(the smaller the value, the faster the shut-off).

Values that are too large can lead to overheating and
triggering of the STB.

Reset time

05-500

30

Setting of the reset time for the I-controller.

Small values lead to fast controller response and can lead to
vibrations.

Adjusting this value can lead to overshooting the controller.

Modgrad on

0 %-100 %

100 %

Setting the modulation depth at which the next heat
generator in the sequence should be connected.

The connection can take place at the end of the remaining
idle time.

Modgrad off

0 %-100 %

80 %

Setting the modulation depth at which the last heat
generator in the current sequence should be shut off.

Min modgrad

0 %-100 %

00 %

Setting the modulation depth at which the next heat gen-
erator should be connected.

The connection of the next heat generator only takes place
if the resulting modulation depth for the individual heat
generator following connection exceeds the value set here.

For operation with the maximum number of burners,
Modgrad On must be set to "00%" and Min. Modgrad
must be set to the minimum modulation depth for the heat
generator-levels.

Modgrad WW

40 %-100 %

100 %

Setting the target modulation depth for the heating appli-
ances in hot water mode.

WE sequence 1

1-2-3-4-5-6-7-8

1-3-2

-4-5-6-7-8

Setting the sequence in which the heating appliances go into
operation at sequence 1.

WE sequence 2

1-2-3-4-5-6-7-8

3-1-2

-4-5-6-7-8

Setting the sequence in which the heating appliances go into
operation at sequence 2 (for two stage heat generators, the
second stage is always switched after the first stage).

Cascade - continued

Level 4 - SPECIALIST - Description of parameters and settings - continued

33