8 strain gage wiring, 8 strain, Gage – LINK Systems 5100-8 Tonnage & Analog Signal Monitor User Manual
Page 60: Wiring

 
 
 
 
Doc
#:
L-802-1110 Page
58 Rev.
02
4) Place the hardened drill fixture provided with
the direct mounting strain gage kit in position 
adjacent to the scribed line. Use a number 3 
drill to drill a 5/8" deep hole in the mounting 
surface through the center hole position of the 
drill fixture. Tap the hole for a 1/4 x 28 thread. 
Bolt the drill fixture securely to the mounting 
area, as shown in Figure 32. 
Drill
Fixture
Drill
Fixture
5) Use a number 3 drill to drill 5/8” deep holes in
the mounting surface through the remaining 
four holes in the drill fixture. Tap the holes for 
a 1/4 x 28 thread after removing the drill 
fixture. 
NOTE:
Do not attempt to locate and drill 
mounting holes without using the 
drill fixture. The hole pattern 
Figure 32: Strain Gage Drill Fixture
 
 
must be precise.
6) De-burr the mounting holes and wipe the
mounting area with a clean rag.
 
7) Mount the strain gage as shown in Figure 
33. Make certain that the washers provided 
with the strain gage kit are placed over the 
strain gages, not under them. Torque the 
1/4 x 28 bolts to 150 in-lbs. A calibrated 
torque wrench is the preferred tool to torque 
the bolts. 
8) Mount the protective cover box provided in
the strain gage kit, if used, centrally over the 
strain gage. It is important to mount the 
cover box before calibration begins. The 
cover box mounting holes may slightly 
change the strain sensed by the strain gage. 
LST-1000
Strain Gage
6.7.2 Intermediate Weld Pad Mounting
1) Select the desired mounting locations for the strain gages. 
 
2) Remove paint, oil, grease, etc., to obtain a bare metal surface slightly larger than the LST-1000 
strain gage.
3) Clean the mounting surface with a solvent, removing all contaminants.
Washers
LST-1000
Strain Gage
Washers
Figure 33: LST-1000 Strain Gage Mounting