beautypg.com

Clearances to combustible materials, Ground level, Rooftop – Reznor R8HE Unit Installation Manual User Manual

Page 8

background image

8

Clearances to Combustible Materials

These units are certified as combination heating and

cooling equipment for outdoor rooftop or ground level

installations. Units may be installed on combustible

flooring or class A, B, or C roofing material when used

with bottom supply and return air ducts as long as the

following requirements are met:

• If using bottom discharge with return air ducts a roof

curb must be installed prior to unit installation. See

Rigging and Hoisting section for setting of the unit.

• Sufficient clearance for unobstructed airflow through the

outdoor coil must also be maintained in order to achieve

rated performance. For information about locating the
equipment, see

page 5

.

Figure 3. Ground & Rooftop Installation

2”

ROOFTOP INSTALLATION

GROUND LEVEL INSTALLATION

ACCESSORY

ROOF CURB

Ground Level

Ground level installations must be located according to

local building codes or ordinances and these requirements:

• Clearances must be in accordance with those shown

in

Figure 1 (page 5)

.

• A suitable mounting pad must be provided and be

separate from the building foundation. The pad must be

level to ensure proper condensate disposal and strong

enough to support the unit’s weight. The slab height

must be a minimum of 2” (5cm) above grade and with
adequate drainage. See

Figure 3

.

• Remove and discard the horizontal Supply and Return

duct covers located on the rear of the unit. Form duct

attachment flanges by bending the sheet metal outward

90 degrees along the perforated lines.

• Firmly attach ductwork directly to these flanges with

screws or other approved mechanical connections and

not to the Supply/Return air panels to avoid damage to

internal components of the equipment. Use approved

duct sealing methods to ensure an air and watertight

seal is achieved.

Rooftop

Rooftop installations must be located according to local

building codes or ordinances and these requirements:

• The roof must be capable of handling the weight of the

unit. Reinforce the roof if necessary For unit weights,
see

Table 7 (page 27)

.

• The appropriate accessory roof curb must be installed

prior to unit installation. The roof curb must be square

and level to ensure proper condensate drainage. See

Figure 2 (page 6)

.

Please follow all instructions

provided with the kit.

• Secure roof curb or frame to roof using acceptable

mechanical methods per local codes.

NOTE: Make sure

the two supports beneath the unit have been removed.

IMPORTANT NOTES TO INSTALLER

• When setting the roof curb for installation, routing and

securement of the gas heat exchanger condensate

drain line must be determined and installed prior to

setting the unit on the curb. It is recommended to drill

a 1.00”-1.25” diameter hole through the roof below

the rectangular opening located in outer close off curb

panel (G) of Nordyne offered curbs, approximately 15”

in from the short side of curb and 1”-2” in from the long

side of curb. If drilling a hole is not an option, routing the

condensate drain hose over to the duct passage opening

with enough slope is acceptable as long as drain line is

secured to curb and duct, ensuring no kinks or traps can

form between the collector box drain or interior of the

building. Leave a minimum of 24” drain line extending

out the top of roof curb front close off panel (G) for

passage through unit bottom and connection to unit

drain when unit is being set. See unit or Condensate/

Vent Drain Kit (P/N-922485) instructions for completion

of the drain connection.

• It is recommended no non-serviceable connections are

introduced in the drain line between unit drain connection

and an accessible area within the building interior.