beautypg.com

Carrier 39L User Manual

Page 81

background image

— Displays the latest service date on the local in-

terface device. The last 2 service dates are displayed at the
Building Supervisor.

TEST FUNCTION — The test function operates the Quick
Test diagnostic program.

— Displays the status of all inputs.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

— Tests the outputs.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

— Tests the electric heaters. Unit must be config-

ured for electric heat to access this subfunction. See
Example 5.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

— Tests the stages of direct expansion (DX) cool-

ing. Unit must be configured for DX cooling to access this
subfunction.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

— Takes the unit out of Quick Test.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

NOTE: The unit must not be operating during the Quick Test
function. Set HOA switch to OFF and follow the test pro-
cedure. Set HOA switch to AUTO only as required during
testing.

To reach a particular test, enter its subfunction number

and then scroll to the desired test by pressing

. A test

can be terminated by pressing

; pressing

after a test

has started terminates the current test and advances the sys-
tem to the next test. Once in the next step, you may start
the test by pressing

, advance past it by pressing

, or

back up by pressing

. When testing is complete, exit the

Quick Test by pressing

and then

; this MUST

be done to restore the unit software to automatic control.

If the keyboard is not used for 10 minutes, the display

returns to the rotating default display. Press

and

to exit Quick Test and then press

to restart the test

procedure.

Example 5 — Using Quick Test

KEYBOARD

ENTRY

DISPLAY

RESPONSE

COMMENTS

ELEC HT

Factory test of electric heat
subfunction of test function

EHS1

Stage 1 test

STG1 TST

Pressing ENTR starts the fan test.
Fan automatically starts. There is an
11-second delay while the inlet
guide vanes open and the heat stage
is enabled. When the electric heat
stage should be running, the display
shows EHS ON. Test remains on
until another key is pressed

EHS2

Pressing the down arrow key
advances the system to stage 2 test.
Any stage may be selected. Press
the

key until the desired stage is

displayed, then press ENTR to start
the test

EXIT TST

If no other test is desired, exit Quick
Test. Fan shuts off, last electric heat
stage shuts off, and IGVs close

TST CMPL

Test is completed. Unit resumes
automatic control

Programming Functions

SERVICE FUNCTION — The service function allows
the operator to verify or change factory and field configu-
rations. The service subfunctions are listed below. (See
Table 13 for details.) Refer to Table 16 for configuration value
ranges and defaults.

— Use this subfunction to log on before perform-

ing any subfunction in Factory Configurations (

),

and to log off after completing service subfunctions. See
Example 6.

Example 6 — Logging On and Logging Off

Service Function

KEYBOARD

ENTRY

DISPLAY

RESPONSE

COMMENTS

TO LOG ON:

LOG ON

Ready for password to be
entered

LOGGEDON

Operator can now use
service functions

TO LOG OFF:

LOG OFF

Ready for operator to log off

LOGD OFF

Logged off — password
protection enabled

81