beautypg.com

4 - common installation, Bus splicing, Power bus – Rockwell Automation 1512B MV Controllers, 200/400A Two-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 43: Chapter 4, Common installation, Chapter

background image

Rockwell Automation Publication 1500-UM055G-EN-P - May 2013

35

Chapter

4

Common Installation

Bus Splicing

Power Bus

1. The power and ground bus splice kit can be found in a package mounted

to the front of the shipping skid.

2. Refer to

Access to the Power Bus on page 26 of Chapter 3

for either

standard or ArcShield enclosure.

3. For a 1200A power bus, assemble the splice bars as shown in

Figure 38

.

Tighten the nuts to 65 N•m (48 lb•ft).
For a

2000A power bus, assemble the splice bars as shown in

Figure 39

.

Tighten the nuts to 65 N•m (48 lb•ft).

ATTENTION: This procedure requires contact with medium voltage
components. To avoid shock hazards, lock out incoming power before working
on the equipment (refer to

Power Lock-out Procedure on page 47 of Chapter 5

).

Verify with a hot stick or appropriate voltage measuring device that all circuits
are voltage free. Failure to do so may result in severe burns, injury or death.

IMPORTANT

Verify that the structure series numbers on the splice kit package
match the structure series number found on the cabinet nameplate
(refer to

Starter Identification on page 2 of Chapter 1

for details

regarding the nameplate).

IMPORTANT

Attach the bus links to the cabinet on the left side first - as viewed from
the front of the unit.

IMPORTANT

Always place the bus clamps on the rear side of each main horizontal
bus or splice bar, as viewed from the front of the unit.