Top exiting load cables, E for, Top exiting load – Rockwell Automation 1512B MV Controllers, 200/400A Two-High Cabinet, Standard and Arc-Resistant Enclosure User Manual
Page 27

Rockwell Automation Publication 1500-UM055G-EN-P - May 2013
19
Installation – Standard Enclosure
Chapter 2
Top Exiting Load Cables
5. Load cables for the bottom power cell should be routed first. Pull the
cables into the cabinet through the appropriate opening (see
).
Run the cables behind the current transformer mounting plate and into
the bottom power cell.
Figure 18 - Load Cable Conduit Openings (Top Exit Shown)
6. For the top power cell, pull the cables into the cabinet through the
7. Connect the cables to the current transformers and tighten the
connections to 65 N•m (48 lb•ft).
8. Connect cable shields to the ground lug.
9. Reinstall the cable duct boot and reassemble the cabinet.
Ground Lug
Load Cable Conduit
opening for cables from
bottom power cell
Load cable Conduit
Opening for cables
from top power cell
Top of Cabinet
ATTENTION: Ensure all barriers are replaced before re-energizing the
equipment. Failure to do so may result in electrical faults and cause
damage to equipment or serious injury to personnel.