5. Secure the sections together using the 1/4-20 self-tapping screws. Thread

the screw through the 7 mm (0.281 in.) clearance hole to the
corresponding 6 mm (0.219 in.) pilot hole. To access the front clearance
holes of the left-side cabinet, open the medium voltage doors. To access the
rear clearance holes remove the rear covers of the starter. If rear access is
not available, refer to

Front Access– Access to Power Bus on page 11

.

6. Secure the right section to the floor using 12 mm (1/2 in. [M12]) floor

mounting bolts (refer to

Anchoring on page 7

).

Figure 6 - Joining Sections

Access to the Power Bus

Rear Access

1. Remove the hardware securing the center rear bus access cover (see

Figure 7

).

2. Remove the center rear bus access cover.

Fron

t

Fro

nt

Side Bus
Access Cover

0.219 Pilot
Holes (5x)

0.281 Pilot
Holes (5x)

0.281 Pilot
Holes (5x)

0.219 Pilot
Holes (3x)

ATTENTION: This procedure requires contact with medium voltage
components. To avoid shock hazards, lock out incoming power before working
on the equipment (refer to

Power Lock-out Procedure on page 47 of Chapter 5

).

Verify with a hot stick or appropriate voltage measuring device that all circuits