Bottom exiting load cables, Figure 37 – Rockwell Automation 1512B MV Controllers, 200/400A Two-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 42

background image

34

Rockwell Automation Publication 1500-UM055G-EN-P - May 2013

Chapter 3

Installation – Arc-Resistant Enclosure (ArcShield)

Bottom Exiting Load Cables

5. Load cables for the top power cell should be routed first. Pull the cables

into the cabinet through the appropriate opening (see

Figure 37

). Run the

cables behind the current transformer mounting plate and into the top
power cell.

Figure 37 - Load Cable Conduit Openings

6. For the bottom power cell, pull the cables into the cabinet through the

appropriate opening (see

Figure 37

).

7. Connect the cables to the current transformers and tighten the

connections to 65 N•m (48 lb•ft).

8. Connect cable shields to the ground lug.

9. Reinstall the cable duct boot and reassemble the cabinet.

TIP

Follow steps 1-4 from previous section.

Load Cable Conduit Opening for

Cables from Top Power Cell

Load Cable Conduit Opening for

Cables from Bottom Power Cell

Bottom of Cabinet

ATTENTION: Ensure all barriers are replaced before re-energizing the
equipment. Failure to do so may result in electrical faults and cause