Delivery, Transport and Setting Up
3.3.4 Storage after delivery
If the incubator is initially to be stored after delivery: Read the storage conditions from page
65 .
3.4
Setup
The incubator can be placed either on the ground or on a table (work surface). When doing
this, ensure that the appliance is positioned exactly horizontally
.
The installation site must be
level and able to reliably carry the weight of the incubator (see page 18 ). Do not place the ap-
pliance on an inflammable surface.
A power connection must be available at the installation site in accordance with the connec-
tion data on the nameplate (see page 18 ).
The distance between the wall and the rear of the chamber must be at least 15 cm. The clear-
ance from the ceiling must not be less than 20 cm and the side clearance from the wall not
less than 8 cm ( Fig. 7 ). Sufficient air circulation in the vicinity of the chamber must be guaran-
teed at all times.
FP
FP
FP
FP
Fig. 7
Minimum clearance from walls and ceiling