Installation, operation and maintenance manual 23, 8 awg) insulated copper cable, (see figure 17) – ERICO 3000 ERITECH SYSTEM User Manual

Page 25

background image

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

23

www.erico.com

To bond the downconductor inside a
conductive non-ferromagnetic mast pipe
or conduit, secure two stainless steel cable
ties around the downconductor at every
1 m (40 in.) or at 2 m (80 in.) intervals
with their tails left on, alligned at 180°
to each other so that when fed into
the pipe, they maintain contact with
the inside wall of the pipe, (see figure
17). The maximum length of the cable
installed inside the mast pipe or conduit
should not exceed 35 m (114 ft).

The 6 mm

2

(8 AWG) copper cable used to

connect the structure bonding braid to the
structure must be one continuous length.
Joins in this cable would represent a
potential maintenance issue.

Any metallic surfaces that the down-
conductor may be secured to, if possible,
should be electrically connected to the
structural steel work.

Also, when using a metallic mast (ie: free
standing light pole), the structure bonding
braid must be connected to the top of the
metallic mast using 6 mm

2

(8 AWG)

insulated copper cable, (see figure 17).

Metallic mast pipe or conduit

Downconductor

2 x stainless steel

cable ties at 180°

with tails left on

1 to 2 m (40-80 in.)
intervals as appropriate

reestandin metallic

mast where

downconductor

cannot be secured

to inside of mast

tructure bondin

cable attached to

top of freestandin

mast

Figure 17: Electrical bonding of downconductor within metallic mast section or pipe.