Cu mounting, Cu electrical installation, Product completeness check – 2N Lift8 v1.6.0 User Manual
Page 28: Putting in operation
28
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Product Completeness Check
Check whether the product package is complete before installation:
1 central unit
1 main bus terminal
4 bus connection terminals
4 wall plugs
4 wall plug screws
8 cable ties
1 battery connecting cables
1 brief manual
1 warranty sheet
drilling template
CU Mounting
It is recommended to install the
in a room that is secured against unauthorised
CU
persons, such as the lift machine room, switching station etc. On an easily accessible
place there is a risk of telephone line misuse or SIM card misappropriation .
The
is mounted on a wall with the included wall plugs and screws.
CU
CU Electrical Installation
Putting in operation
Keep the
disconnected from the mains.
CU
Loosen the three screws on the upper cover of the CU.
Move the upper cover of the
in such a way that you can remove it.
CU
When removing the cover, proceed with caution, be careful about the earth wire
connecting the cover with the
bottom part. Do not disconnect the wire unless
CU
there is a reason to do so!
Using the slide-on terminals supplied with the device, connect the Audio Units,
splitters (if there are 2 and more lift shafts) and other components of the system
with the
Adhere to polarity!
CU.
Install a PSTN, GSM or UMTS module unless installed on the
. Abide by the
CU
instructions given in the Instructions for Use of the given module (refer to Subs.
2.7 or 2.8).
Connect an analogue telephone line to the PSTN module if used (use a telephone
connector or the terminal board on the module). Do not forget to connect an
antenna to the GSM/UMTS module is used and insert a SIM card!
Connect the rechargeable battery jumper link (see the next subsection –
Rechargeable Battery State Check) to activate the rechargeable battery function.
Replace the upper cover on the
and tighten the cover fitting screws. Doing so
CU
make sure that the earthing wire is connected to the cover!
Connect the
power cable to a 230V socket.
CU
Caution
If you connect one lift shaft only, it is not necessary to connect the
splitters. Use the splitters only if you want to connect 2 or more lift shafts.