7 start up check list, Electrical – Hale FoamLogix 6.5 User Manual
Page 101

101
FoamLogix 3.3 / 5.0 / 6.5 Installer / Operations Manual
p/n: 029-0021-68-0
Sta rt -Up Chec k L is t
❑
3.7
START UP CHECK LIST
Before energizing the apparatus and the Hale FoamLogix system for the
first time make sure the following items are checked:
Electrical
Refer to the following for an overview of electrical connections:
●
Figure 3-33: “Dual Tank Electrical Harness Overview” on page 88
●
Figure 3-34: “Control/Display Unit Mounting Dimensions” on page 89
●
For cable harness overviews, see Section “ 9 Plate Drawings,” beginning on
page 170.
●
Figure 3-35: “Distribution Box Connections” on page 90
❑
Tank LOW level sensor wires extended, if necessary, and connected to
main cable harness (C10, C11).
❑
Tank LOW level sensor wires sealed against moisture with silicone seal-
ant provided.
❑
Tank LOW level sensor(s) function properly.
❑
For single tank operation, if the Hale MST is not used, check that the
tank select jumper plug is installed at connector C8.
❑
Control cable connection at distribution box is correct and tight.
❑
Flow sensor cable properly connected to main cable harness (C3).
❑
All cables and wires are secured and protected from damage during
operation.
❑
Control and flow sensor cables properly folded and secured; radio anten-
nas, power lines and equipment away from cables.
❑
Foam pump and motor assembly properly grounded using flat ground
strap.
❑
Correct voltage provided. Direct current, negative (–) ground.
❑
Adequate current, 60 AMPS minimum, available. Main power direct to
battery, battery switch or solenoid without primer or other accessories
tied in.
❑
Primary electrical and ground connections tight and protected from cor-
rosion with silicone sealant.
❑
Splices in wires sealed from moisture using adhesive filled heat shrink
tubing.