Long horizontal pipes

• Install on slightly ascending pipe section.
• If not possible, make sure that the flow velocity is high enough to prevent air, gas or vapor to

collect in upper part.

• In partially filled pipes, the clamp-on flowmeter will report incorrect flow rates, or not

measure.

Vertical pipelines

CAUTION!
Make sure that the rail is not mounted at the highest point (risk for air bubbles) or at the lowest
point (risk for particles) of the pipe.

Figure 3-2: Long horizontal pipes

CAUTION!
Make sure that the pipe is fully filled at all times.

INFORMATION!
Both ascending and descending flow directions are measurable.

Figure 3-3: Mounting on vertical pipelines is possible