beautypg.com

Operation, 1 preparation for operation, 2 wram-up operation and regular operation – Yokogawa IR400 User Manual

Page 32: 2 warm-up operation and regular operation

background image

4 - 1

IM 11G02N01-01E

4.1 Preparation for operation

(1) Tube and wiring check

Double-check if tubes of the gas sampling and exhaust ports are correctly connected.

Double-check for proper wiring.

4.2 Warm-up operation and regular operation

(1) Operation procedure

1) Turn ON the power switch on the front panel of the analyzer unit.

The measurement screen appears on the front display panel in 1 or 2 seconds.

2) Wait for about 4 hours until the instrument is warmed up.

About 4 hours are required until the instrument allows accurate measurement.

Note) When in warm-up, the concentration reading may be beyond.

upper limit of range or

lower limit of range.

But, it is not an error.

3) Setting of various set values

Perform the various settings according to “Chapter 6. Setting and Calibration”.

4) Zero calibration and span calibration

Perform zero calibration and span calibration after warm-up operation.

Refer to “Chapter 6.9. Calibration”.

5) Introduction and measurement of measuring gas

Introduce the measuring gas into the analyzer unit before starting measurement.