2 start checklist and system start, Start checklist and system start -42 – YSI IQ SensorNet 2020 XT Terminal User Manual
Page 72
Installation
System 2020 XT USB
3 - 42
ba76019e01
12/2012
3.9.2
Start checklist and system start
Before starting the system, carry out the system check using the
following checklist. Always carry out the check
before the initial commissioning
before any further commissioning if the system has been previously
extended or modified.
Starting the system
Switch on the voltage supply of the MIQ power supply module(s).
Start checklist
1 Is the sum of the power consumption of the components
smaller than the sum of the power delivery of all power supply
modules (see section 3.3)?
2 Are all IQ S
ENSOR
N
ET
components correctly connected with
one another (see section 3.5)?
3 Are all SN terminator switches correctly set (see section
3.9.1)?
4 Is the MIQ power supply module correctly connected to the
voltage supply?
5 Do the line voltage and line frequency agree with the data on
the name plate of the MIQ power supply module?
6 Are all IQ sensors ready for measuring, e.g. a D.O. sensor
filled with electrolyte solution?