121

As a general rule, the test result is positive if the equipment shows its immunity, for the duration
of the application of the test, and at the end of the tests the EUT fulfills the functional
requirements established in the technical specification.”

The user has to make this determination by observing the unit under test. At the end of the test, the GUI will
pop up a dialog box asking the operator to assess the state of the EUT. If the EUT is still functional, the
operator may answer Yes when prompted. If not, he should answer no. The response to this query is
incorporated as a PASS or FAIL result in the test report.

13.7

EN 61000-4-29 Test Reports

At the end of a test run, the operator can generate a test report by clicking on the “Print report” button. EN
61000-4-29 test reports include all test setup information and test results. User provided information at the
bottom of the 4-29 screen is included as well.

The report format and test report headers can be selected from the Option, IEC Test Report menu but
needs to be done before opening the IEC 429 test screen. The selected format (Printer, Text File or MS
Word) applies to all IEC immunity tests. MS Word reports are automatically saved in the C:\Program
Files\California Instruments\Mxgui\Reports directory.